Saturday 17 November 2007

Extension - Week 5 (Nearly there)

Earlier this week the joiners completed their work inside plasterboarding the partition between the family room and utility room, and building a cupboard & fitting the window in the utility room.






Towards the end of the week the taper and plasterer arrived.





On Friday the Plumber started fitting the lead to the flat part of the roof.


Poor Casper and Jasmin, with all the commotion they have had to stop feuding and keep each other company to get through this period of change.


Not long to go now.

Saturday 10 November 2007

Extension - Week 4

Day 12 - Plumbing run and floor insulated.


Day 13 - Floor layed and wiring run in.




Day 14/15 - Ceiling and exterior walls insulated and plasterboarded


Day 16 - Plasterboarding outer walls complete and partition constructed.
Pitched roof tiling complete outside



Monday 5 November 2007

Kemnay Firework Display

You really had to be there to appreciate it, not bad for a local village, a bit like the Rosehearty firework display but without the massive bonfire.

Saturday 3 November 2007

Extension - Week 3

Day 7 - Scaffolding erected
Day 8 - Roof trusses complete and pitch boarded out
Day 9 - Flat roof boarded out and eaves fitted

Day 10 - Roof felted and batons fitted for tiles


Day 11 - Dining room window relocated into extension and door fitted






I have also been busy inside. The new breakfast bar area is finished