The builders were only here 2 days this week, so the progress is not as far as was expected. One of the partners of the firm doing the scaffolding and roof tiles suddenly died, and being a small family run business there was no-one working for most of the week.

Day 5 - Concrete foundations to DPC level



Day 6 - Kit erected





I have been busy destructing inside and running TV cables etc. The knock-out panel between the living room and dining room is gone and all downstairs carpets and skirtings up. Just a shell of a house at the moment, but the kids are loving running around in the space. The cats are looking a bit sorry for themselves though.


The scaffolders arrive on Monday so it should be a productive week ahead and a different picture completely for the next blog entry.